Greater Victoria’s sewage treatment project may have to undergo revisions in order to save money, with the chair of the board overseeing the project warning of likely cost over-runs.

Don Fairbairn, chair of the core area wastewater treatment project board, raised the possibility of revisions in a presentation to the wastewater treatment committee of the Capital Regional District.

“Our confidence [in meeting budget] is not high,” he said. “We are feeling concerned that there is a likelihood that we will not be able to deliver the program within the control budget.”

Fairbairn said the project board will have a better understanding of the cost pressures facing the $765-million project by mid-March, when Ernst and Young, as well as KWL Consulting Engineers will have returned their respective assessments.

Funding for the project comes from three sources: the provincial and federal governments responsible for a total of $459 million and local governments responsible for $306 million.

Ernst and Young will look at what Fairbairn calls the “root causes” of the current cost pressures. “Is it related to things that we can control? Is it related to things we can’t control? Is it related initially to the quality of the budgets utilized to establish our control budget?”

Escalating material, labour, and design costs have forced the project board to lower its confidence that the project won’t exceed the budget, said Fairbairn. Other factors include the completion deadline of Dec. 31, 2020 for the project, input from stakeholders, and geo-technical risks, he said.

KWL Consulting Engineers will also give the board an independent cost analysis of the remaining elements still requiring procurement, he said. The public heard about three per cent of the project remain un-procured. KWL Consulting’s assessment would also consider whether the not-yet-procured elements add “utility value” to the project.

“As a consequence of this study, we may or may not, I don’t know, come to the conclusion that some of that infrastructure could be deferred,” he said. “We should come to some determination as whether or not there is value in that infrastructure — what should be built, what could be deferred, or some of it ought not to be built.”

RELATED:$765 million McLoughlin plant the final suggestion for sewage treatment

Fairbairn said the outcome of this review is open. Should the review recommend changes, it would be up to the core area liquid waste management committee to recommend changes to the CRD board. “There would be robust discussion around that,” he said.

Esquimalt Mayor Barb Desjardins, who chairs the core area liquid waste management committee, said she is not pre-supposing anything at this stage. “Mr. Fairbairn has expressed a gut feeling, and they are going to get that information.”

Touching on various aspects of the project, Fairbairn said it remains on schedule.

“We have a high level of confidence that we will deliver this project,” he said. “We will have an operating wastewater treatment system that complies with all regulations, all laws, no later than Dec. 31, 2020.”


Like us on Facebook and follow us on Twitter

wolfgang.depner@saanichnews.com

Just Posted

BC SPCA overwhelmed with cats, kittens needing homes

Large number of cruelty investigations, plus normal ‘kitten season’ to blame

Cross-examination begins for Oak Bay dad accused of killing daughters

Andrew Berry is charged in the deaths of six-year-old Chloe and four-year-old Aubrey in 2017

Camosun mechanical engineering project solve real-world problems

Showcase included projects that confound conventional wisdom, garner industry interest

Arenas, fitness centre ready for action after significant flood at Saanich recreation centre

Library branch, archives remain closed after Thursday night flood

Midway will open early at the 2019 Saanich Fair

This year the fair will pilot a “sneak peek” and the main stage will feature April Wine

B.C. sockeye returns drop as official calls 2019 ‘extremely challenging’

Federal government says officials are seeing the same thing off Alaska and Washington state

Expanded support to help B.C. youth from care attend university still falling short

Inadequate support, limited awareness and eligibility restrictions some of the existing challenges

Ethnic media aim to help maintain boost in voting by new Canadians

Statistics Canada says new Canadians made up about one-fifth of the voting population in 2016

Dog attacked by river otters, Penticton owner says

Marie Fletcher says her dog was pulled underwater by four river otters in the Penticton Channel

POLL: Should there be a ban on gas-powered leaf blowers?

We’ve all heard them, and most likely cursed them under our breath.… Continue reading

Greater Victoria wanted list for the week of Aug. 23

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

Wife charged in husband’s death in Sechelt

Karin Fischer has been charged with second-degree murder in the death of her husband, Max

B.C. Hydro applies for rare cut in electricity rates next year

Province wrote off $1.1 billion debt to help reverse rate increase

Most Read