Aluminum planks are installed for the multi-use walkway on the bridge span at the end of December, the surface cyclists and pedestrians will use to travel across the new Johnson Street Bridge. (Photo courtesy Jonathan Huggett)

Span to be installed this month for Victoria’s Johnson Street Bridge

Existing bridge, marine channel closures expected

The Johnson Street bridge is getting closer to its March completion date as the bridge span is installed this month, leaving just minor tasks to finish the project for good.

The span – the bridge deck where vehicles, pedestrians and cyclists will cross – is tentatively scheduled to be lifted Saturday Jan. 27, potentially closing the existing bridge to traffic for the day. The marine channel will be closed for nine days while workers bolt the span to the rings and perform test bridge lifts. The Dynamic Beast, a giant crane barge able to lift over 800 metric tonnes, will arrive a day earlier.

“If it doesn’t lift at the end of the nine-day period, we’re in trouble,” said engineer and project manager for the bridge Jonathan Huggett, adding that this work will ensure the bridge deck lift mechanism is fully operational.

“This is do or die.”

Construction crews will work overnight if needed to get the project done, he said, but installation could still be delayed pending availability of the crane and unfavourable weather conditions.

RELATED: Johnson Street Bridge’s steel rings, lower counterweight lifted into place over weekend

RELATED: Orca-inspired sculpture pitched for Victoria Johnson Street Bridge park

In August, Huggett indicated the bridge would “look almost complete” by Christmas for the $105-million bridge replacement, however the span installation was pushed back to this month. Workers have been using that time to perform work on the span prior to the lift, Huggett said, rather than after it had been attached. Installing the span will be a major step to completing the project, but after those nine days, there is still work to be done.

“Obviously after that there’s still a lot of odds and ends left to do, but we will have demonstrated after the nine-day period that we can lift the bridge,” Huggett said. “It’s a huge step on that day.”

After the span is installed, workers will place concrete beams to close the gap between the two sides of the bridge, touch up the paint, and perform tests to ensure all parts are operating properly.

Huggett expects crowds to gather and watch as the giant steel structure is lifted into place, as was the case when the two 290-tonne steel rings were installed in early December, and when the steel parts originally arrived from China in early fall.

“It will be spectacular,” he said.

The bridge is on schedule for completion in March after years of delays.

MORE STORIES on the Johnson Street Bridge replacement 

lauren.boothby@vicnews.com

 

Hundreds of bolts connect one of the 290-tonne steel rings to the bascule pier. (Photo courtesy of Jonathan Huggett)

The south ring of the Johnson Street Bridge sits on the equalizer, a cradle that holds up the bridge, with wheels that rotate as the rings of the bridge move that will lift the bridge span. (Photo courtesy of Jonathan Huggett)

Just Posted

Langford loses bid to host Amazon HQ2

Mayor hopes to attract more tech jobs to city

Woodwynn Farms to be shut down and sold

The rehabilitation program at Woodwynn Farms is being shut down. According to… Continue reading

Pedestrian in hospital with non-life-threatening injuries after being struck in View Royal

Incident closed Island Highway for several hours Wednesday night

Tenants sought for Metchosin elementary school

Cushman Wakefield Ltd. Victoria will be responsible for leasing the space

Monster trucks invade Victoria

Traxxas Monster Truck Tour stops at Save-On Foods Memorial Centre this weekend

WestJet appeals lost bid to scrap harassment lawsuit

Airline argues judge was wrong to have dismissed the company’s application to strike the legal action

Can U.S. border guards search your phone? Yes, and here’s how

Secretary of homeland security explains a new policy that let’s border guards check phones

‘Beautiful writer’ Nancy Richler dies of cancer in Vancouver hospital

Montreal-born author spent most of her adult life in B.C. as a fiction writer and novelist

Jury convicts spear-wielding Duncan man in 2015 Ladysmith RV park murder

Trever George Meers used a handmade spear to stab Rayna Johnson at the Campers Corners RV Park

Students frustrated by UBCO response to harassment allegations

Students on the Kelowna campus were unaware of resources and worried about lack of communication

Opinion: Dare to be smarter

Just say no works for more than just substance abuse

‘Sing Me a Song’ about B.C. for a chance at $1,000 contest prize

Entries due by March 30 for lieutenant-governor’s British Columbia-themed competition

Facing reality of death, B.C. man learns real meaning of life

Even while preparing for the end, something inside Keven Drews won’t let him stop living

Most Read