Undersea cable pitched for clean energy

A company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids

Wind farm development in northeastern B.C. Proponents of a new power line between Vancouver Island and Washington say it would make wind power a more stable source.

VICTORIA – With BC Hydro struggling to control electricity rate increases and cutting back on private power acquisition, a company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids.

Sea Breeze Power Corp. wants to build a 50 km transmission cable under the Strait of Juan de Fuca to connect substations near Port Angeles and Victoria. To finance the project, it’s looking for a 10-year deal to assemble surplus U.S. power and sell it to BC Hydro at a flat rate of $69 per megawatt hour.

Sea Breeze CEO Paul Manson said the power purchase would finance the construction of the cable and deliver a steady source of electricity to B.C. at lower cost than new sources built in the province. It would also improve power quality and reliability for Vancouver Island residents, he said.

First proposed in 2006, the project has received environmental permits from both sides of the border. It was rejected by the B.C. Utilities Commission, which approved upgrading the existing power line from the B.C. mainland to Vancouver Island instead.

Sea Breeze developed a wind project at Cape Scott on northern Vancouver Island, and has plans and permits for other wind sites on the B.C. coast and the Peace River region. Manson said the Juan de Fuca cable would stabilize wind power supply on the B.C. coast, where wind speeds peak in winter, with inland Washington sites where it’s windiest in summer.

Manson said U.S. policy led to major wind development that leaves the the Pacific Northwest with an excess of power in spring, meaning the Washington power utility has paid BC Hydro to take its excess when hydro dams are full.

The cable would also give B.C. more capacity to buy cheap overnight coal and nuclear power from the U.S., which BC Hydro already does with its main connecting line along Interstate 5, he said.

Energy Minister Bill Bennett said the Juan de Fuca cable is one of many proposals that came forward as BC Hydro developed its integrated resource plan. That plan estimates that with conservation and efficiency improvements in B.C., the province will need more electricity supplies within eight years.

The company has not yet demonstrated that it can assemble the firm electricity it proposes to sell, and the project has “a pretty steep slope to climb,” Bennett said.

 

Just Posted

SD61 to install new water fountains over lead concerns

They’re installing 350 new water fountains in local schools due to concerns over elevated levels of lead in the water system

West Shore firefighters band together to support men’s health

More than $8,200 raised for Movember campaign

Omnibus zoning bylaw sent for revisions to prevent blanket upzoning in downtown Victoria

More than 10 downtown properties identified by Downtown Residents Association

UPDATE: Four vehicle crash on Sooke Road snarls traffic in Colwood

Sooke Road reopens to traffic in both direction

Belmont students, staff reunite family with long-lost war medal

Medal belonged to Sharon Hoover’s great-great uncle

VIDEO: That’s a wrap: Be a Santa to a Senior packages ready to go out

Program hands out more than 600 gifts to Greater Victoria seniors

Owl found dead after eating rat poison leaves B.C. woman concerned

After finding the owl on her Surrey property, Christine Trozzo says the poison is a concern for kids

Change to CPP death benefit panned as insufficient to cover funeral costs

Funeral Services Association of Canada lobbied governments to raise the value to $3,580

Shelbourne Community Kitchen vies for $20,000 prize

Epicure Foundation, based in North Saanich, will give five groups $20,000 each

Woman in Nanaimo accidentally hands over diamond ring with spare change

Incident happened Wednesday at about 7 p.m. at parking lot near Nanaimo’s boardwalk

B.C. woman brain injured in crash as a baby gets $1.1 million in damages

Trial heard the woman was 16 months old, being carried by her mother when they were both hit

Optimistic Victoria whale watching company invests in new vessel

Banner 2017 tourist season helps Prince of Whales decide to boost service

Victoria cycling advocate makes pitch lor lower speeds on local roads

Group points to evidence suggesting 30 km/h speed limit would save money, lives

Most Read