UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Homeless campers of Namegans Nation head to Oak Bay

Roughly 30 members of roving tent city settle at Cattle Point in Uplands Wednesday

Sooke school registrations increase

New schools are needed but funding slow to come

B.C. moves ahead with speculation tax despite mayors calling for changes

Oak Bay mayor says he was hoping for a different outcome

Legalization at the legislature: Victoria celebrates with free cannabis

Longtime cannabis activist Dana Larsen hands out free joints, seeds, plants

UPDATE: Pat Bay Highway traffic moving again after motorcyclist rear-ended

Three vehicle collision stalled traffic in southbound lane Wednesday shortly before 4 p.m.

Watch: Saanich responds to mock emergency for ammonia Leak

Hazmat suits, emergency centre respond to mock ammonia leak

Find your future at Black Press career fair in Victoria

More than 70 booths expected at Bay Street Armoury on Oct. 25

POLL: Do you support amalgamation for communities in the Capital Region?

Residents in Victoria and Saanich will be voting on Oct. 20 on… Continue reading

Jagmeet Singh says marijuana pardons are not enough

Trudeau government will streamline pardon process for Canadians convicted of simple possession of marijuana in the past

VIDEO: Courtenay marks legalization by passing out free joints

Leaf Compassion celebrates new marijuana law in Courtenay

Caregivers banned from smoking, growing cannabis around children-in-care: MCFD

Ministry has limited cannabis use for caregivers, stating it may “pose a risk to children and youth.”

Jusu adds hemp extract to the menu in Greater Victoria

Food and beverage product to be enhanced with hemp extract

Cheaper strains sell out within minutes on online BC Cannabis Store

Province says new strains will become available in the coming months

Most Read